Where your deposit lives
Deposits should sit in escrow or behind a bank guarantee until completion, never in the developer’s operating account. If the contract does not say which, we do not sign.
A completion date that means something
A long-stop date, after which you can walk away with your deposit, turns the developer’s estimate into a promise. Without one, a delay is your problem.
Specification and snagging
The specification attached to the contract is the one you get. A clause allowing "equivalent" substitutions should name what counts as equivalent, and snagging should be fixed within a set number of days.